NSPRJ1 · North Sea · 500 MW
Control tower
North Sea Project 1 — decisions, EAC health, and contingency headroom.
Budget
$157.6m
Approved baseline
Committed
$157.6m
100% of budget
Actual
$30.0m
To period cut
EAC
$162.6m
Actual + ETC
Variance
$5.0m
Contingency
$6.8m
85% remaining
Asks for decision
Control queue
- 01HighCAPEX.WTG.VO · Turbine variations allowance
EAC is $5.0m over the locked snapshot
Approve the variation from contingency, or challenge it before period close.
Project controls
Story for the room
EAC moved +$5.0m against the locked budget
The movement is the turbine variation. The rest of the book is tracking the September 2024 snapshot.
VoWD is $30.0m
Most of the recognised work is the first turbine milestone. Cash still follows the contract curve.
Control intelligence
EAC moved +$5.0m against the locked budget
The movement is the turbine variation. The rest of the book is tracking the September 2024 snapshot.
VoWD is $30.0m
Most of the recognised work is the first turbine milestone. Cash still follows the contract curve.