Cost control for project finance — from VOWD to shareholder pack

Seeded with North Sea Project 1 (USD) and Pacific Array Offshore Wind (EUR). Click through the loop below — figures are illustrative; edits stay in this browser.

Enter cost bookShareholder packNo login · public demo
  1. 01

    Portfolio position

    Two live books, two reporting currencies — USD North Sea and EUR Pacific. Ledger never mixes them.

    Start here →

  2. 02

    Cost book & Cadence FX

    Line-level commitments, payment schedule, and FX you can see and override before it hits reporting.

    Open North Sea →

  3. 03

    VOWD → propose → match

    Value of work done feeds the payment run. Controllers propose, then match invoices to settle.

    Operating loop →

  4. 04

    Month-end & shareholders

    Freeze the period, run the checklist, then pack FX and export the shareholder report.

    Close the month →

  5. 05

    Scenario sandbox

    Fork the live book, stress cost or cash timing, compare deltas, promote only when ready.

    What-if →

Portfolio

Cost position

Each project keeps its own reporting currency. Ledger does not add dollars to euros.

USD book · 1 project

Locked budget

$157.6m

VOWD

$30.0m

EAC

$162.6m

EUR book · 1 project

Locked budget

€2.36bn

VOWD

€929.2m

EAC

€2.40bn

NSPRJ1

North Sea Project 1

North Sea · 500 MW · Late stage development

Over locked +3.2%

Locked

$157.6m

VOWD

$30.0m

EAC

$162.6m

Variance

$5.0m

Planned cumulative cost and value of work doneUS$0.0$50.0m$100.0m$150.0m$200.0m25-1126-0126-0426-0726-1027-0127-0628-01
Planned cumulative VOWD to dateFull cost book

PA-1

Pacific Array Offshore Wind

Taiwan Strait · 900 MW · Construction

Over locked +1.8%

Locked

€2.36bn

VOWD

€929.2m

EAC

€2.40bn

Variance

€42.8m

Planned cumulative cost and value of work done€0.0€1.25bn€2.50bn€3.75bn€5.00bn25-1126-0126-0326-0927-0628-06
Planned cumulative VOWD to dateFull cost book