Client preview — North Sea (USD) and Pacific Array (EUR) are seeded. Figures are illustrative · walkthrough
Reporting period
Drives cash windows, reports, VOWD context, and the shareholder pack as-of date. Prototype: localStorage. New projects & scenarios stay on this browser.
Append-only
Audit
Append-only record of WBS, cost edits, Cadence milestones, payment ingest/match, VOWD, snapshots, FX, and the shareholder lock.
| When | Project | Entity | Detail | User |
|---|---|---|---|---|
| 2026-03-18 09:12 | PA-1 | Forecast | CBS 3.3 ETC raised for WTIV standby | m.okada |
| 2026-03-15 16:40 | PA-1 | Forecast | Variation VO-INS-003-07 submitted at €31.2m | m.okada |
| 2026-03-12 11:02 | NSPRJ1 | FX | EURUSD curve point 2026-03-01 set to 1.16 | treasury |
| 2026-03-04 08:20 | NSPRJ1 | VOWD | Monopile lot flagged for reprice | controller |
| 2026-02-28 14:11 | NSPRJ1 | Invoice | Harbour Steel Yards monopile lot 1 registered | controller |
| 2026-01-20 10:04 | NSPRJ1 | Invoice | Q1 turbine milestone marked paid | pmo |
| 2025-11-01 00:00 | PA-1 | Snapshot | FID baseline approved at €2.36bn | a.chen |
| 2024-09-17 00:00 | NSPRJ1 | Snapshot | SEP 2024 N4 set as current budget | pmo |