Installation package EAC +€48.3m vs baseline
CBS 3.3 Installation (WTIV) EAC is €323.0m against €265.0m budget. Pending VO-INS-003-07 (€31.2m standby) is the primary driver; residual weather risk remains in ETC.
Recommended action
Decision: approve VO with contingency draw, challenge claim quantum, or rebaseline package 3.
Owner
M. Okada
Decision required