Reporting period
Drives cash windows, reports, VOWD context, and the shareholder pack as-of date. Prototype: localStorage. New projects & scenarios stay on this browser.
PA-1 · Taiwan Strait · 900 MW
Control tower
Pacific Array Offshore Wind — decisions, EAC health, and contingency headroom.
Budget
€2.36bn
Approved baseline
Committed
€2.32bn
99% of budget
Actual
€929.2m
To period cut
EAC
€2.40bn
Actual + ETC
Variance
€42.8m
Contingency
€85.6m
69% remaining
Asks for decision
Control queue
- 01CriticalCAPEX.TI.PRI · Installation (WTIV)
Installation package EAC +€48.3m vs baseline
Decision: approve VO with contingency draw, challenge claim quantum, or rebaseline package 3.
M. Okada
- 02HighProject
Contingency draw path exceeds period plan
Confirm contingency policy for installation claims before period close.
A. Chen
- 03Medium4.3 · Export & grid connection
Export & grid under-committed vs spend plan
Accelerate shortlist award or lift ETC contingency explicitly.
M. Okada
Story for the room
EAC moved +€17m this period
Almost entirely CBS 3.3. Standby variation (+€31.2m pending) offset by a −€14m release in array cable ETC after factory acceptance.
Commitment coverage is tight on foundations
Package 3 committed value already exceeds baseline. Further installation risk must come from contingency or rebaseline — not silent ETC growth.
Period 2026-03 is in closing
Cut-off held. Three late foundation certificates staged in; control log updated. Ready for controller sign-off once VO decision lands.
Control intelligence
EAC moved +€17m this period
Almost entirely CBS 3.3. Standby variation (+€31.2m pending) offset by a −€14m release in array cable ETC after factory acceptance.
Commitment coverage is tight on foundations
Package 3 committed value already exceeds baseline. Further installation risk must come from contingency or rebaseline — not silent ETC growth.
Period 2026-03 is in closing
Cut-off held. Three late foundation certificates staged in; control log updated. Ready for controller sign-off once VO decision lands.