PA-1 · Taiwan Strait · 900 MW

Control tower

Pacific Array Offshore Wind — decisions, EAC health, and contingency headroom.

Fixed-bottom offshore windBaseline 2025-11-01Reporting EURA. Chen · Project Director

Budget

€2.36bn

Approved baseline

Committed

€2.32bn

99% of budget

Actual

€929.2m

To period cut

EAC

€2.40bn

Actual + ETC

Variance

€42.8m

Breach+1.8% vs baseline

Contingency

€85.6m

69% remaining

Asks for decision

Control queue

Open exceptions
  • 01CriticalCAPEX.TI.PRI · Installation (WTIV)

    Installation package EAC +€48.3m vs baseline

    Decision: approve VO with contingency draw, challenge claim quantum, or rebaseline package 3.

    M. Okada

  • 02HighProject

    Contingency draw path exceeds period plan

    Confirm contingency policy for installation claims before period close.

    A. Chen

  • 03Medium4.3 · Export & grid connection

    Export & grid under-committed vs spend plan

    Accelerate shortlist award or lift ETC contingency explicitly.

    M. Okada

Story for the room

What changed this period

EAC moved +€17m this period

Almost entirely CBS 3.3. Standby variation (+€31.2m pending) offset by a −€14m release in array cable ETC after factory acceptance.

Commitment coverage is tight on foundations

Package 3 committed value already exceeds baseline. Further installation risk must come from contingency or rebaseline — not silent ETC growth.

Period 2026-03 is in closing

Cut-off held. Three late foundation certificates staged in; control log updated. Ready for controller sign-off once VO decision lands.

Control intelligence

  • EAC moved +€17m this period

    Almost entirely CBS 3.3. Standby variation (+€31.2m pending) offset by a −€14m release in array cable ETC after factory acceptance.

  • Commitment coverage is tight on foundations

    Package 3 committed value already exceeds baseline. Further installation risk must come from contingency or rebaseline — not silent ETC growth.

  • Period 2026-03 is in closing

    Cut-off held. Three late foundation certificates staged in; control log updated. Ready for controller sign-off once VO decision lands.

Control log — append-only
2026-03-18 09:12Z
ledger.exception.opened exc_1 · Installation overrun
a91c·04e2
2026-03-15 16:40Z
ledger.commitment.variation_submitted VO-INS-003-07 · €31.2m
c3f0·88ab
2026-03-14 11:05Z
ledger.actuals.period_staged 3 certificates · CBS 3.1
91dd·2201
2026-03-01 08:00Z
ledger.period.opened 2026-03
e2aa·7710
2025-11-01 00:00Z
ledger.baseline.approved FID baseline · €2.36bn
0b17·ff3c