CriticalOverrunCAPEX.TI.PRI · Installation (WTIV)opened 2026-03-06
Installation package EAC +€48.3m vs baseline
CBS 3.3 Installation (WTIV) EAC is €323.0m against €265.0m budget. Pending VO-INS-003-07 (€31.2m standby) is the primary driver; residual weather risk remains in ETC.
Recommended action
Decision: approve VO with contingency draw, challenge claim quantum, or rebaseline package 3.
Owner
M. Okada
Decision required
HighContingencyProjectopened 2026-03-12
Contingency draw path exceeds period plan
€38.4m already drawn (31%). If VO-INS-003-07 is approved from contingency, remaining headroom falls below the board threshold of 55%.
Recommended action
Confirm contingency policy for installation claims before period close.
Owner
A. Chen
Decision required
MediumCommitment lag4.3 · Export & grid connectionopened 2026-03-10
Export & grid under-committed vs spend plan
CBS 4.3 is 91% of ETC uncommitted. Grid connection window still assumes award by May — commercial risk if tender slips.
Recommended action
Accelerate shortlist award or lift ETC contingency explicitly.
Owner
M. Okada
Decision required
MediumFXCAPEX.TI.PRI · Installation (WTIV)opened 2026-03-15
USD towage PO FX move +€1.1m
PO-INS-119 booked at 1.08; reporting FX now 1.16. Covered in installation ETC band; flag for treasury.
Recommended action
Hedge residual USD exposure or accept in EAC band.
LowLate actuals3.1 · Monopile fabricationopened 2026-03-14
Three foundation invoices outside period cut
Harbour Steel Yards certificates dated 28 Feb arrived 14 Mar — staging as period 03 with prior-period note.
Recommended action
Accept into March actuals; annotate audit log.