NSPRJ1 · North Sea · 500 MW

Control tower

North Sea Project 1 — decisions, EAC health, and contingency headroom.

Fixed-bottom offshore windBaseline 2024-09-17Reporting USDNorth Sea HoldCo · 60%

Budget

$157.6m

Approved baseline

Committed

$157.6m

100% of budget

Actual

$30.0m

To period cut

EAC

$162.6m

Actual + ETC

Variance

$5.0m

Breach+3.2% vs baseline

Contingency

$6.8m

85% remaining

Asks for decision

Control queue

Open exceptions
  • 01HighCAPEX.WTG.VO · Turbine variations allowance

    EAC is $5.0m over the locked snapshot

    Approve the variation from contingency, or challenge it before period close.

    Project controls

Story for the room

What changed this period

EAC moved +$5.0m against the locked budget

The movement is the turbine variation. The rest of the book is tracking the September 2024 snapshot.

VoWD is $30.0m

Most of the recognised work is the first turbine milestone. Cash still follows the contract curve.

Control intelligence

  • EAC moved +$5.0m against the locked budget

    The movement is the turbine variation. The rest of the book is tracking the September 2024 snapshot.

  • VoWD is $30.0m

    Most of the recognised work is the first turbine milestone. Cash still follows the contract curve.

Control log — append-only
2026-03-12 10:20Z
ledger.exception.opened CAPEX.WTG.VO · $5.0m
ns4a·19c0
2024-09-17 00:00Z
ledger.baseline.approved SEP 2024 N4 · $157.6m
ns01·44e2