Reporting period
Drives cash windows, reports, VOWD context, and the shareholder pack as-of date. Prototype: localStorage. New projects & scenarios stay on this browser.
NSPRJ1 · North Sea · 500 MW
Period control
North Sea Project 1 — period 2026-03 is closing. Work exceptions before close.
Budget
$157.6m
Approved baseline
Committed
$157.6m
100% of budget
Actual
$30.0m
To period cut
EAC
$162.6m
Actual + ETC
Variance
$5.0m
Contingency
$6.8m
85% remaining
Controller desk
Period status
closing
Open exceptions
1
Pending variations
1
Draft commitments
0
Working EAC
$162.6m
Contingency drawn
$1.2m
Asks for decision
Control queue
- 01HighCAPEX.WTG.VO · Turbine variations allowance
EAC is $5.0m over the locked snapshot
Approve the variation from contingency, or challenge it before period close.
Project controls
Control intelligence
EAC moved +$5.0m against the locked budget
The movement is the turbine variation. The rest of the book is tracking the September 2024 snapshot.
VoWD is $30.0m
Most of the recognised work is the first turbine milestone. Cash still follows the contract curve.