Ledger
LP

Reporting period

Drives cash windows, reports, VOWD context, and the shareholder pack as-of date. Prototype: localStorage. New projects & scenarios stay on this browser.

Shareholder pack

Reporting to shareholders

Board pack from live book or a sealed snapshot: locked FX, L3 roll-up, ownership for the pack only, narrative, and Excel / PDF / PowerPoint export.

Before you export

  • 3 unmatched cash signals in Match payments.
  • 3 open Cadence payments still unsettled.

Pack setup

Curve into USD (no fixed overrides) · as of 2026-03-31 · np-9bae7096

NSPRJ1 · Late stage development · budget SEP 2024 N4

Report only

Rates into USD

Optional overrides; blank cells use the Currency curve on the pack as-of date.

FromCurve @ 2026-03-31Override (optional)
EUR → USD1.160000

Locked budget · USD

$157.6m

Pack $157.6m

VOWD · USD

$30.0m

Pack $30.0m

EAC · USD

$162.6m

Pack $162.6m

This pack · USD

$159.1m

Live cost book

Ownership (pack only)

Does not change project master data.

ShareholderSharePack (USD)
60%
US$95,431,500
40%
US$63,621,000

By stage

StageControl (USD)Pack (USD)

CAPEX

Capital Expenditures

US$157,612,500US$159,052,500

WBS roll-up (L3 board cut)

WBSDescriptionControl (USD)Pack (USD)
CAPEXCapital ExpendituresUS$157,612,500US$159,052,500
CAPEX.CABCAB PackageUS$14,612,500US$14,612,500
CAPEX.CAB.PRICable Supply Agreement - Contract PriceUS$14,612,500US$14,612,500
CAPEX.EPCEPC ManagementUS$6,600,000US$6,600,000
CAPEX.EPC.CERCertificationUS$6,600,000US$6,600,000
CAPEX.FOUFOU PackageUS$26,400,000US$27,840,000
CAPEX.FOU.PRIFoundation Supply Agreement - Contract PriceUS$26,400,000US$27,840,000
CAPEX.WTGWTG PackageUS$110,000,000US$110,000,000
CAPEX.WTG.PRITurbine Supply Agreement - Contract PriceUS$105,000,000US$105,000,000
CAPEX.WTG.VOTurbine Supply Agreement - VariationsUS$5,000,000US$5,000,000

Pack notes

  • Board pack for North Sea Project 1 (NSPRJ1) · Late stage development.
  • Amounts in the pack currency (USD) use Curve into USD (no fixed overrides). Operational control stays in USD.
  • Cost basis: live cost book.
  • Locked budget basis: SEP 2024 N4.
  • Ownership split applied to the pack total only: North Sea HoldCo 60%; Baltic Infra Partners 40%.