Reporting period
Drives cash windows, reports, VOWD context, and the shareholder pack as-of date. Prototype: localStorage. New projects & scenarios stay on this browser.
Forecast vs locked budget
Cost book
Each line is VAT unless you switch it to WHT. Net is before tax. Gross adds VAT, deducts WHT withheld at source, or grosses up a topped-up WHT.
Focused from Snapshots: CAPEX.TI.PRI · 1 line(s).
Amounts before tax.
Last locked budget
€2.36bn
Sealed snapshot
VOWD to date
€929.2m
Confirmed work
Cost to complete
€1.47bn
Remaining forecast
Cost at completion
€2.40bn
VOWD + CTC
Variance vs locked
€42.8m
EAC above locked budget
Items missing info
1
Category, FX, or tax
Planned cost
S-curve
| WBS | Line item | Description | Date | VoWD | Cash out | Tax | Net | Remove |
|---|---|---|---|---|---|---|---|---|
CAPEX | Capital Expenditures | — | — | 1,066,200,000.00EUR | — | — | 1,066,200,000.00EUR | |
PackageCAPEX.WTG | WTG Package | — | — | 855,000,000.00EUR | — | — | 855,000,000.00EUR | |
Work item | — | — | 855,000,000.00EUR | |||||
PackageCAPEX.CAB | CAB Package | — | — | 142,000,000.00EUR | — | — | 142,000,000.00EUR | |
Work item | — | — | 142,000,000.00EUR | |||||
PackageCAPEX.TI | T&I | — | — | 69,200,000.00EUR | — | — | 69,200,000.00EUR | |
Work item | 2 milestones | — | 69,200,000.00EUR | — | VAT | 69,200,000.00EUR | ||
Milestone 1 · settledCAPEX.TI.PRI.1 | 38,000,000.00EUR | |||||||
Milestone 2CAPEX.TI.PRI.2 | 31,200,000.00EUR |