Reporting period
Drives cash windows, reports, VOWD context, and the shareholder pack as-of date. Prototype: localStorage. New projects & scenarios stay on this browser.
Forecast vs locked budget
Cost book
Each line is VAT unless you switch it to WHT. Net is before tax. Gross adds VAT, deducts WHT withheld at source, or grosses up a topped-up WHT.
Focused from Snapshots: CAPEX.WTG.PRI · 1 line(s).
Amounts before tax.
Last locked budget
$157.6m
Sealed snapshot
VOWD to date
$30.0m
Confirmed work
Cost to complete
$132.6m
Remaining forecast
Cost at completion
$162.6m
VOWD + CTC
Variance vs locked
$5.0m
EAC above locked budget
Items missing info
0
Category, FX, or tax
Planned cost
S-curve
| WBS | Line item | Description | Date | VoWD | Cash out | Tax | Net | Remove |
|---|---|---|---|---|---|---|---|---|
CAPEX | Capital Expenditures | — | — | Mixed | — | — | Mixed | |
PackageCAPEX.EPC | EPC Management | — | — | 6,600,000.00USD | — | — | 6,600,000.00USD | |
Work itemCAPEX.EPC.CER | Certification | — | — | 6,600,000.00USD | — | — | 6,600,000.00USD | |
Milestone | — | — | 6,600,000.00USD | |||||
PackageCAPEX.WTG | WTG Package | — | — | Mixed | — | — | Mixed | |
Work item | 3 milestones | — | Mixed | — | VAT | Mixed | ||
Milestone 1 · settledCAPEX.WTG.PRI.1 | 30,000,000.00USD | |||||||
Milestone 2 · settledCAPEX.WTG.PRI.2 | 35,000,000.00EUR | |||||||
Milestone 3CAPEX.WTG.PRI.3 | 40,000,000.00USD | |||||||
Work item | — | — | 5,000,000.00USD | |||||
PackageCAPEX.FOU | FOU Package | — | — | 24,000,000.00EUR | — | — | 24,000,000.00EUR | |
Work item | 2 milestones | — | 24,000,000.00EUR | — | VAT | 24,000,000.00EUR | ||
Milestone 1 · settledCAPEX.FOU.PRI.1 | 12,000,000.00EUR | |||||||
Milestone 2CAPEX.FOU.PRI.2 | 12,000,000.00EUR | |||||||
PackageCAPEX.CAB | CAB Package | — | — | 2,400,000.00USD | — | — | 2,400,000.00USD | |
Work item | 1 milestone | — | 2,400,000.00USD | — | VAT | 2,400,000.00USD | ||
Milestone 1CAPEX.CAB.PRI.1 | 2,400,000.00USD |