Ledger
LP

Reporting period

Drives cash windows, reports, VOWD context, and the shareholder pack as-of date. Prototype: localStorage. New projects & scenarios stay on this browser.

Forecast vs locked budget

Cost book

Each line is VAT unless you switch it to WHT. Net is before tax. Gross adds VAT, deducts WHT withheld at source, or grosses up a topped-up WHT.

Focused from Snapshots: CAPEX.FOU · 1 line(s).

Amounts before tax.

Last locked budget

$157.6m

Sealed snapshot

VOWD to date

$30.0m

Confirmed work

Cost to complete

$132.6m

Remaining forecast

Cost at completion

$162.6m

VOWD + CTC

Variance vs locked

$5.0m

EAC above locked budget

Items missing info

0

Category, FX, or tax

Planned cost

S-curve

Planned cumulative cost and value of work doneUS$0.0$50.0m$100.0m$150.0m$200.0m25-1126-0126-0426-0726-1027-0127-0628-01
Planned cumulative VOWD to dateAll 5 lines
WBSLine itemDescriptionDateVoWDCash outTaxNetRemove
CAPEX
Capital Expenditures——Mixed——Mixed
PackageCAPEX.EPC
EPC Management——6,600,000.00USD——6,600,000.00USD
Work itemCAPEX.EPC.CER
Certification——6,600,000.00USD——6,600,000.00USD
Milestone
—
—
6,600,000.00USD
PackageCAPEX.WTG
WTG Package——Mixed——Mixed
Work item
3 milestones—Mixed—VATMixed
Milestone 1 · settledCAPEX.WTG.PRI.1
30,000,000.00USD
Milestone 2 · settledCAPEX.WTG.PRI.2
35,000,000.00EUR
Milestone 3CAPEX.WTG.PRI.3
40,000,000.00USD
Work item
—
—
5,000,000.00USD
PackageCAPEX.FOU
FOU Package——24,000,000.00EUR——24,000,000.00EUR
Work item
2 milestones—24,000,000.00EUR—VAT24,000,000.00EUR
Milestone 1 · settledCAPEX.FOU.PRI.1
12,000,000.00EUR
Milestone 2CAPEX.FOU.PRI.2
12,000,000.00EUR
PackageCAPEX.CAB
CAB Package——2,400,000.00USD——2,400,000.00USD
Work item
1 milestone—2,400,000.00USD—VAT2,400,000.00USD
Milestone 1CAPEX.CAB.PRI.1
2,400,000.00USD